| Effective implementation management and timely contract administration |
B: 119. Project Management |
|
10/31/2028 |
|
| Continue proactive Environmental Compliance work |
C: 165. Produce Compliance Documentation |
|
10/31/2028 |
|
| Cultural Surveys to BPA |
D: 165. Cultural Resource Surveys |
|
10/31/2028 |
|
| Coordination completed and budget change request submitted |
E: 191. Subbasin Coordination |
|
10/31/2028 |
|
| Program support provided |
F: 191. Upper Columbia Habitat Prioritization Support |
|
10/31/2028 |
|
| Education and Outreach |
G: 99. Upper Columbia education and outreach |
|
10/31/2027 |
|
| Develop or update (out-year) prioritized Habitat Project list: Upload to CBFish |
H: 114. Project Identification and Selection Process & Coordination w/BPA |
|
04/30/2028 |
|
| Complete project design |
I: 175. Methow - Upper Chewuch floodplain enhancement Design |
|
10/31/2028 |
|
| Hummingbird Enhancement Project design |
J: 175. Methow - Chewuch Hummingbird Design |
|
10/31/2028 |
|
| Complete Final Designs |
K: 175. Entiat - Pope Entiat River Restoration Design |
|
10/31/2027 |
|
| Complete final design. |
L: 175. Wenatchee - Little Wenatchee River floodplain restoration Design |
|
10/31/2027 |
|
| Complete draft final design. |
M: 175. Wenatchee - White River Restoration - Private land - Design |
|
10/31/2028 |
|
| Restoration project design completed |
N: 175. Okanogan - Salmon Creek RM8 Floodplain Design |
|
11/30/2027 |
|
| Complete design process |
O: 175. Okanogan - Omak Creek Instream Complexity Design |
|
10/31/2028 |
|
| Riparian planting completed |
P: 47. Okanogan - Antoine Valley Ranch Revegetation |
|
10/31/2028 |
|
| Construction Management Complete |
Q: 100. Okanogan - Salmon Creek RM8 - Construction Management |
|
12/31/2027 |
|
| Stream complexity enhanced |
R: 29. Okanogan - Salmon Creek RM8 - Install LWD |
|
12/31/2027 |
|
| Completed side channel hydrologic improvements |
S: 30. Okanogan - Salmon Creek RM8 - Realign, connect, and/or create channel |
|
12/31/2027 |
|
| Floodplain enhanced |
T: 180. Okanogan - Salmon Creek RM8 - Enhance Floodplain |
|
12/31/2027 |
|
| Floodplain wetland enhanced |
U: 181. Okanogan - Salmon Creek RM8 - Enhance Floodplain Wetland |
|
12/31/2027 |
|
| Enhancement of riparian floodplain benches |
V: 47. Okanogan - Salmon Creek RM8 Revegetation |
|
10/31/2028 |
|
| Construction Management Complete |
W: 100. Methow - Chewuch Hummingbird - Construction Management |
|
10/31/2028 |
|
| Complexity enhanced |
X: 29. Methow - Chewuch Hummingbird - Install LWD |
|
10/31/2028 |
|
| Completed channel construction |
Y: 30. Methow - Chewuch Hummingbird - Realign, connect, and/or create channel |
|
10/31/2028 |
|
| Complete Ramsey Creek Reconnection |
Z: 85. Methow - Chewuch Hummingbird - Remove Passage Barrier |
|
12/31/2027 |
|
| Floodplain reconnected |
AA: 180. Methow - Chewuch Hummingbird - Enhance Floodplain |
|
10/31/2028 |
|
| Floodplain wetlands enhanced |
AB: 181. Methow - Chewuch Hummingbird - Enhance Floodplain Wetland |
|
10/31/2028 |
|
| Plant Vegetation |
AC: 47. Methow - Chewuch Hummingbird - Vegetation Planting |
|
10/31/2028 |
|
| Casia Lodge Beaver Creek Floodplain Complexity |
AD: 29. Methow - Casia Lodge Beaver Creek Wood Enhancement PASS THROUGH |
|
12/31/2027 |
|
| Floodplain improvements compelted |
AE: 180. Methow - Casia Lodge Beaver Creek Wood Enhancement PASS THROUGH |
|
12/31/2027 |
|
| Develop technical site level information and spatial products |
AF: 122. On-call professional services |
|
10/31/2028 |
|
| Completed Progress (Annual) Report |
AG: 132. UCHIP annual report 2025-2026 |
|
10/31/2028 |
|
| Completed Progress (Annual) Report |
AH: 132. UCHIP annual report 2026-2027 |
|
10/31/2028 |
|